Case Archives
Project cycle time, in 24 sectors
42 engagements across CAPEX, engineering, R&D, shutdowns and multi-project environments.
AerospaceAerospace & DefenceAutomotiveAviation MROBuilding materialsCementChemicalsEducationHeavy engineeringInfrastructureManufacturingMedical devicesMiningNuclearPharmaceuticalPharmaceutical R&DPortsPowerReal estateShipbuildingSolarSteelTextilesWind energy
- Aarti IndustriesAarti Industries – Project Timelines Improved by 30–40% During ExpansionFacing a large, market-driven specialty chemicals expansion with a lean management team, Aarti Industries restructured execution, enabling the same team to double execution speed and improve project timelines by 30–40%.Chemicals
- Action TESAAction TESA – ₹350 Cr MDF Expansion Completed On-TimeFor a ₹350 Cr MDF brownfield expansion in the wood panel industry, Action TESA adopted a Focus & Finish execution model, achieving higher progress with fewer resources and significantly reducing execution firefighting.Building materials
- AlmarazAlmaraz Nuclear Power Plant – Major Shutdown Completed Ahead of ScheduleManaging complex engineering upgrades and a shutdown workforce scaling from 400 to 3,000 personnel, Almaraz executed critical safety and capacity projects, completing the shutdown three days early and the power uprate six days early.Nuclear
- BoeingBoeing Satellite Unit – Throughput Doubled, Cycle Time Cut by 30%Boeing's satellite development unit improved execution across complex programs, doubling throughput, cutting cycle times by 20–30%, and completing key projects in as little as 65 days against 92 planned.Aerospace
- BRPLBRPL – HGMS Project Delivered On-Time Against a 30% Faster TargetA leading merchant pellet manufacturer aimed to add HGMS in 14 months to improve Fe recovery. Realization deployed a Critical Chain implementation in two weeks and delivered the project on time.Power
- BUIDCoBUIDCo – 681 km Work Front Released in 6 Months Across 15 CitiesBUIDCo undertook a $190m urban infrastructure program across 15 cities in Bihar. Critical Chain implementation released 681 km of work front within 6 months and doubled the design approval rate across water, sewerage, road, and drainage projects.Infrastructure
- Century PanelsCentury Panels – MDF and Laminate Plants Commissioned in 16.5 MonthsCentury Panels executed a greenfield MDF and laminate project at Kadapa under extended monsoons and only 30% civil manpower availability, achieving laminate commissioning in 14 months and MDF in 16.5 months.Building materials
- Delta Air LinesDelta Air Lines – 62% Fewer Cancellations and $60M Monetized from MROManaging aircraft engine repair, base maintenance, and line maintenance for a large commercial fleet with limited spare engines and high inventory costs, operations were restructured to reduce queues and improve flow, cutting cancellations by 62% and unlocking $60M without adding assets.Aviation MRO
- Dr. Reddy's LaboratoriesDr. Reddy's – Project Completion Up 85%, Due-Date Performance at 80%A global pharmaceutical company managing large NPD portfolios reduced project overload, improved focus, and lifted completion rates by 85%, raising due-date performance from 20% to 80% without adding resources.Pharmaceutical
- Granules IndiaImproving R&D Portfolio Flow and Due Date Performance at Granules IndiaFifteen months after a Critical Chain implementation across its API and Formulation Development R&D portfolios, Granules India moved due-date performance from 20% to 70%.Pharmaceutical R&D
- ISGECISGEC Heavy Engineering – 32% Growth Achieved with Predictable ExecutionA multi-location heavy engineering EPC manufacturer running 50+ concurrent projects improved execution visibility, recovered delays, met a 25% growth target in eight months, and achieved 32% growth over two years.Heavy engineering
- Jai Raj IspatJai Raj Ispat – Delayed Integrated Steel Plant Restored to a Predictable FinishAn Indian steel manufacturer executing a 0.45 MTPA integrated steel plant recovered from a nine-month delay, stabilised execution with limited resources, and completed the full complex within 16 months.Steel
- JindalJindal Paradip Port – Phase 1 Delivered Ahead of ScheduleA greenfield 25 MTPA coal, limestone and steel port was active on every front but had no operable route from jetty to rake. Execution was restructured around one integrated coal circuit, completing the jetty and the first silo ahead of projection and raising structural erection output more than threefold.Ports
- JindalJindal Sohar – 72-Meter Iron Ore Grinding Ball Mill Commissioned in 6 MonthsA large iron ore pelletization facility at Jindal Sohar faced execution congestion and slipping milestones. By stabilizing priorities and work fronts, a 72-meter iron ore grinding ball mill was erected and commissioned in six months.Steel
- Jindal RealtyJindal Realty – 96% Milestones Achieved with 25–35% Cycle-Time ReductionA large real estate developer executing precast-based residential projects restructured portfolio execution, enabling milestone reliability, recovery from delays, and 25–35% cycle-time reduction while doubling annual construction output.Real estate
- Jindal SteelJindal Steel Limited, Raigarh: Delivering the Centre of Excellence Ahead of ScheduleJindal Steel's Centre of Excellence was yet to begin physical execution, with vendors working to independent schedules and completion projected for February 2027. The facility was completed on 5 September 2026, nearly six months ahead of projection.Steel
- Jindal SteelJindal Steel Odisha – 5.5 MTPA Hot Strip Mill Commissioned in Record 29 MonthsA stalled, coordination-heavy brownfield Hot Strip Mill with limited resources and repeated disruptions was stabilized, sequenced, and delivered in 29 months, against the earlier industry benchmark of 38 months.Steel
- Jindal SteelJindal Steel Raigarh — 70% Reduction in Shutdown Duration of RHH LineRHH line upgradation at Raigarh faced brownfield constraints, equipment readiness gaps and high coordination complexity. Through phased execution and full-kitting, shutdown duration was reduced from ~60 days to 21 days.Steel
- L&TL&T Shipbuilding – Shipyard and Shiplift Delivered in Record 28 MonthsA greenfield mega shipyard built on India's east coast under cyclones, vendor failures, and manpower shortages, where execution flow was stabilized to recover delays and commission in record time.Shipbuilding
- MEILMegha Engineering & Infrastructures – Oil Rig Execution Cycle Reduced by 25%Executing complex onshore oil and gas rig projects, fabrication, assembly, and site execution were restructured to restore flow, cutting rig turnaround time by 20–25% and enabling predictable deliveries.Infrastructure
- NTPCNTPC Khargone – Ultra-Supercritical Thermal Power Project Delivered On-TimeIndia's largest power producer executed an ultra-supercritical thermal power project involving 30+ contractors and thousands of drawings, achieving all major milestones on time through stabilized execution and early-warning visibility.Power
- Prism CementPrism Cement – Combined Upgrade and Annual Shutdown Delivered 13 Days EarlyA preheater upgrade and the annual maintenance shutdown were combined into one stoppage, concentrating more than 200 activities onto shared workfronts. Execution was reorganised into 35 handover batches, completing in 50 days against the 63-day plan.Cement
- Procter & GambleProcter & Gamble Pharmaceuticals – 300% Throughput Increase Per Quarter in a YearA $2B pharmaceutical R&D organization managing complex drug development projects faced rising workload without additional resources. After implementing CCPM, quarterly completions increased from 3 to 12+ and due-date compliance improved from 55% to 80%+.Pharmaceutical
- Shyam MetalicsShyam Metalics – Long-Shut Steel Complex Restarted and Commissioned in 16 MonthsAfter acquiring a long-closed steel complex with incomplete engineering and stalled projects, Shyam Metalics stabilized execution flow and achieved mechanical completion of a blast furnace and sinter plant within 11 months.Steel
- Siemens GamesaSiemens Gamesa: ~50% Reduction in Design Cycle Time in High-Uncertainty R&DA complex R&D environment where design cycles extended to two years. Projects faced unclear sequencing, frequent rework, and rigid planning. By restructuring work into a two-tier task framework and reducing over-detailed planning, cycle time fell by around 50%.Wind energy
- Skoda PowerSkoda Power — Achieved 90% On-time Projects with CCPM ImplementationA leading steam turbine manufacturer managing complex EPC and manufacturing projects was facing delays and resource conflicts. With CCPM implementation, on-time delivery improved from ~60% to ~90% and project lead times reduced by ~30%.Power
- SSWLSSWL – 90% On-Time Delivery with 25% Throughput IncreaseSSWL improved wheel manufacturing execution by stabilizing project flow and assembly operations, achieving over 90% on-time delivery, a 25% throughput increase, and clearing a six-month backlog.Automotive
- TAP Air PortugalTAP Air Portugal – 21% Downtime Reduction and €330k Cost SavingsAs rapid route expansion strained aircraft maintenance operations, TAP restructured execution across checks, reducing downtime by 21%, improving productivity, and saving €330,000 while maintaining fleet availability.Aviation MRO
- Tata SteelTata Steel – Finishing Mill Upgrade Completed Ahead of Schedule, $4.4M SavedWhile upgrading its finishing mill to increase annual capacity, Tata Steel executed a high-risk shutdown with 500+ interdependent tasks, completing it in 8.8 days against an 11-day target.Steel
- Terumo MedicalTerumo Medical – Backlog Cleared in 8 Months, Record Execution Times AchievedA global medical device manufacturer supporting regulated cardiac and vascular products faced heavy project overload. By restructuring execution flow, Terumo cleared its backlog in eight months and achieved record delivery times.Medical devices
- Transmission & DistributionTransmission & Distribution — A Common Execution Desync Seen Across Live ProjectsT&D projects faced chronic desynchronization and fragmented execution across multiple agencies. By restructuring around stringing-ready fronts, Realization enabled synchronized progress, improving velocity and energization timelines by up to 40%.Power
- Trident GroupTrident Real Estate – On-Time Despite COVID, NGT and Manpower ConstraintsAmid severe work-front constraints, COVID and NGT disruptions, Trident restructured site execution and manpower flow, achieving critical CC milestones on time, improving throughput, and stabilizing cash flow with the same resources.Real estate
- US NavyUS Navy F/A-18 Maintenance – 40% Higher Throughput, Fewer Aircraft GroundedAn aging F/A-18 fleet was grounding half the Navy's fighter jets due to slow depot maintenance. Execution was stabilized, work in progress reduced, and annual aircraft returns increased from 21 to 30.Aerospace & Defence
- VardhmanVardhman Fabrics – Cotton Yarn Expansion Delivered On-Time with 30% Extra ScopeA large textile manufacturer executing a ₹450 Cr cotton yarn brownfield expansion overcame manpower shortages, supply disruptions, and stoppages, delivering projects on time in 15 months while achieving 30% additional scope.Textiles
- VardhmanVardhman Special Steels – Capacity Expansion Delivered Ahead of ScheduleWhile running at full production, Vardhman expanded its steel plant with two planned shutdowns, completing the project 1.5 months early, minimizing disruption, and bringing additional capacity online faster.Steel
- VIBGYOR Group of SchoolsVIBGYOR – All 6 New Schools Delivered On-Time, Admissions Up 20%A large K–12 education group managing simultaneous school construction and renovations stabilized execution, delivering six new schools on time, completing expansions as planned, and increasing student admissions by 20%.Education
- VIBGYOR Group of SchoolsVibgyor Schools: 70% Reduction in Cycle Time with 90%+ On-Time DeliveryAcross 35–40 campuses, Vibgyor faced 8-month cycle times and growing backlog. Structured portfolio control reduced cycle time to 2.5 months and improved on-time delivery to 90%+.Education
- Vikram SolarVikram Solar – Predictable Project Delivery and Cashflow Aligned ExecutionAs Vikram Solar scaled its EPC portfolio, execution needed stability and cashflow alignment. Projects were restructured to flow in clear phases, reducing rework, improving predictability, and protecting profitability.Solar
- VulcanVulcan International – 250% Faster Wash Plant Execution with the Same ResourcesWhile executing wash-plant brownfield upgrades under resource shortages, material unavailability, and conflicting priorities, execution was reorganized to eliminate start-stop losses, resulting in 30% higher rates and 250% faster delivery without additional manpower.Mining
- VulcanVulcan Mozambique — 90 Day TOC TurnaroundAfrica's largest coal operation was losing about $12 million every month, with roughly three months to reverse direction. Execution was restructured around one governing constraint at a time, reaching a $54 million monthly profit by April.Mining
- VulcanVulcan Mozambique – Achieved 40% Higher Maintenance HoursTo support a rapid ramp-up at Africa's largest coal mine, Vulcan addressed chronic wash-plant downtime, completing almost all maintenance packages during shutdown and achieving 40% higher maintenance hours.Mining
- Yogiji Digi GroupYogiji Digi Group — 37.6% Throughput Increase in 6 MonthsA leading steel equipment manufacturer was struggling with delays and assembly bottlenecks. Within six months, delays dropped by 81% (5.5 months to 23 days) and throughput improved by 37.6%.Manufacturing