Vulcan · Mining
Vulcan Mozambique — 90 Day TOC Turnaround
Challenges
- Losing about $12 million every month, with roughly three months to turn the operation around before the risk of shutdown became real.
- Operating system stretched from the pit at Moatize to washing, stockyards, a rail corridor of roughly 900 kilometres, port unloading and customer shipment.
- Only about 34 to 40 of 77 mining trucks available, a shortage of giant tyres having immobilised much of the fleet.
- Working trucks operating only about 14 hours in a 24-hour mine.
- Giant tyres at roughly $50,000 each against normal lead times exceeding six months.
- Metallurgical coal yield at the 50 MTPA wash plant at about 11 percent.
- Twenty-one trains circulating, yet a round trip taking about 100 to 110 hours.
Our work
- Made cash generation the immediate goal, evaluating actions by their effect on throughput, inventory and operating expense while keeping capital expenditure separate.
- Chose to increase throughput before cutting the organisation, with no mass layoff programme used as the turnaround lever.
- Linked the production plan to customer demand, making customer orders the reference for what should be mined, blended, washed and shipped.
- Concentrated executive attention on one constraint at a time, with weekly reviews on the single issue with the highest effect on flow and cash.
- Measured the complete rail circuit, which showed loading required about 58 hours against about 105 hours consumed at unloading.
- Reduced the active train fleet from 21 to 18 and positioned three rakes as buffers near unloading.
- Introduced predefined departure and arrival slots, detached engines where appropriate to create maintenance windows, and linked incentives to reliable train journeys rather than isolated speed.
Results
- Monthly performance moved from a $12 million loss in February to a $54 million profit in April, reaching approximately $60 million in May.
- Train cycle time fell from about 110 hours to about 60 hours per round trip.
- Coal haulage increased 55 percent.
- Run-of-mine production rose from 2.2 to 2.7 MTPM.
- Metallurgical coal yield improved from 11 to 17 percent, against metallurgical coal carrying 3 to 4 times the value of thermal coal.
“We thank Realization for providing Project Management services through their unique approach and software, Streamliner, for five Wash Plant projects worth $40M in Vulcan, Moatize. In a resource-constrained environment further intensified by supply chain disruptions, Vulcan adopted Realization's Focus-and-Finish methodology and concentrated resources in few critical projects one by one.
Through this approach, Vulcan ensured on time delivery for the entire portfolio while recovering an average 2-3 months in delivery and coordination delays during execution.”
Dr. Mukesh Kumar, CEO, Vulcan Mozambique