Results Gallery
Measurable change in project cycle time
40 engagements across 18 industries. Each one states where the project stood before, and what changed.
Featured
- Yogiji DigiBefore
YD Group manufactures steel processing equipment for major steel producers expanding capacity. Each project involves designing, manufacturing, and assembling thousands of components, with execution cycles of 6-18 months.
AfterRead the case studyProjects completed per month: Increased from 2.1 to 2.6 (+37.6%). Overall project cycle time: Reduced from 14.5 months to 10 months (+45%). Cleared backlogs in ordering & assembly, streamlining workflows. Reduced inventory levels and rework, cutting unnecessary costs.
- Jindal Steel Odisha (JSOL)Before
JSOL embarked on a transformative journey in 2021, unveiling an audacious ₹18000 Cr capital expenditure plan aimed at doubling the capacity of its Angul plant from 6 MTPA to 12 MTPA by FY'24. The projects included HSM, Slab Caster, RMHS, Oxygen plant, and Central Utility.
AfterRead the case studyThe project was completed in 29 months, a record in comparison to similar projects done elsewhere.
- Brahmani River Pellets (BRPL)Before
A beneficiation plant upgradation project for HGMS facility's readiness.
StatusRead the case studyEngagement ongoing.
- ISGECBefore
There were around 50-55 projects running in parallel in machine division.
AfterRead the case studyISGEC had a target of increasing project throughput by 25% in one year. The target was achieved.
- VIBGYORBefore
VIBGYOR set a target of setting up 6 schools in 2019-20, against their usual 2-3 schools a year. Till June, progress was negligible and the general feeling was that none will come on time.
AfterRead the case studyAll 6 schools were delivered on time.
- Jindal RealtyBefore
JRL is one of the leading real-estate developers in North India. In Sonipat, the projects included student hostels, Independent floors, villas and plots, community infrastructure etc. Shortage of precast material and various resources, conflicting priorities and unreliable projections were some of the challenges that caused delays in these projects.
AfterRead the case studyTransparent visibility of the entire portfolio was established in 3 weeks. 96% of planned milestones were achieved. University hostel blocks were delivered in 4.5 months against 7 months achieved earlier.
- HyattBefore
The new hotel construction in Lucknow was running behind schedule. Realization helped Hyatt to plan and strategize for achieving their ambitious target.
StatusEngagement ongoing.
- Vulcan Green, OmanBefore
Upto $3 Bn of Greenfield 5MTPA integrated steel project with 1.4 KM jetty ongoing since 2023. First green hydrogen ready steel plant in Duqm Oman, one of the largest in the GCC.
StatusEngagement ongoing.
- Tata SteelAfterRead the case study
Boiler conversion time was reduced from 300-500 days to 120-160 days, achieving a 68% faster turnaround. The planned shutdown period decreased from 11 days to 8.8 days. Daily revenue generation increased from $2M to $4M.
- Trident GroupBefore
A real estate project that demanded coordination among over 30 vendors and contractors, with significantly lagging procurement. Realization engaged with a target to complete the project in an aggressive timeline of 6 months.
AfterRead the case studyOverall execution throughput was increased by 25%. Despite the additional hurdles posed by the COVID-19 pandemic, the project was successfully delivered on time.
- L&T Heavy Engineering DivisionBefore
Over 2100 projects in the portfolio across 5 manufacturing locations. For the past 15 years, utilizing Critical Chain Project Management in conjunction with Realization's software for on-time delivery.
AfterOn-time delivery increased to 98%.
- Century PlyBefore
MDF Plant in Hoshiarpur, and Laminate Plant in Kolkata.
AfterRead the case studyThe Greenfield MDF project in Hoshiarpur was running late; the project was delivered in 11 months against an aggressive target of 10 months. Brownfield Laminate expansion in Kolkata: previous baseline 18 months, target 11 months, completed in 13 months.
- Kalpataru Projects InternationalBefore
2 EHV transmission line projects in Congo and Ukraine.
AfterKPTL exceeded AOP targets by 30-40%. Empowered the KPTL team to set up a PMO for 4 additional projects in Egypt, Zambia, Uganda and Rwanda.
- Cameroon Mining Action (CAMINA)Before
Greenfield iron ore mine at Kirbi, Cameroon, with re-development of existing port, beneficiation plant, and logistics infrastructure. Realization is engaged to analyse and plan for the shortest possible time to operationalize the mine and associated infrastructure.
StatusEngagement ongoing.
Every engagement
BusinessCementChemicalEPC BusinessEducationGovernmentHotel & HospitalityIT & SoftwareManufacturingMetal & MiningMetals & MiningPaper & TextilePharmaceuticalsPlywoodPowerReal EstateShipbuildingTextile
| Client | Industry | What changed |
|---|---|---|
| Aarti Industries | Chemical | In 3 years, including 6 months of lockdown and stoppages due to COVID, Aarti was able to deliver ₹2000 Cr worth of projects. |
| L&T Shipbuilding | Shipbuilding | Delivered in a record time of 28 months (site execution: 23 months). |
| Dr. Reddy's Laboratories | Pharmaceuticals | Global Generics and PSAI filings increased from 85 in FY09 to 110 in FY10, a 45% improvement in throughput. Cycle time for full drug development reduced from 915 days to 563 days, 40% faster. Due-date performance improved from 20% to 80%. |
| BUIDCo | Government | BUIDCo doubled the speed of work front generation for contractors. 70% work front generated in 18 months to enable execution of ₹520 Cr out of ₹730 Cr. |
| Vulcan International, South Africa | Metal & Mining | First project was delivered in 260 days, against a projection of 340 days. Second project was delivered, with significantly more scope, in 135 days. Both shutdowns for tie-ins were completed on time. |
| SSWL | Manufacturing | Order backlog of 6 months cleared in 6 months. Throughput increased by 25%. On-time performance above 90%. |
| Vardhman Special Steels | Metals & Mining | Project was completed on time (10 months) along with 2 major shutdowns of actual durations 12 and 8 days against a plan of 11 and 8 days. |
| Prism Johnson | Cement | Recovery of 2 months delay in the largest brownfield expansion. |
| Jai Raj Ispat | Metal & Mining | 0.5 MTPA integrated steel plant including blast furnace, SMS, sinter plant, and rolling mill as major packages. Management set ambitious goals to overcome setbacks, aiming for project completion within 6 months. |
| Shyam Metalics | Metal & Mining | An ambitious target to commission and commence production from a new sinter plant, crucial for feeding a new blast furnace. Major project challenges included delayed equipment ordering, execution drawings and resource shortages. |
| Vikram Solar | Power | Despite the COVID impact, project speed increased and two projects were delivered on time despite missing the earlier intermediate milestones. |
| NTPC Solar | Power | The Kawash project was delivered on time and was the fastest among the entire portfolio. |
| Garden Reach Shipbuilders & Engineers | Shipbuilding | Set up and handover of PMO to GRSE within one year as per plan. 15-20% improvement in cycle time for one of their projects was achieved within a year. |
| JMC Projects | EPC Business | JMC's invoicing to DMRC surpassed that of all other contractors, becoming the highest. 30% jump in cash flow within the first 4 months of execution. |
| Welspun | Textile | The capacity expansion was accomplished in 30 months, the most rapid in the textile industry. |
| Vedanta | Metal & Mining | They had to take advantage of the lean period and complete their shutdown within a set timeframe. The target was achieved. |
| Amdocs | IT & Software | Realization helped Amdocs come up with an optimal allocation mechanism to deliver 20% more projects with the same resources. |
| Kanoria Chemicals, Ethiopia | Textile | Greenfield project delivered in 13 months against a similar project previously delivered in 18 months. |
| Nakoda Textile | Textile | Delivered in 10 months, 3 months faster than industry standards. |
| Everest Industry | Manufacturing | The project was delivered on time (11 months). |
| Satvik Logistics | Business | Construction of a logistics park including warehouses in 18 months. Realization strategized and set up the PMO to achieve this aggressive but achievable timeline. |
| PP Rolling Mills | Manufacturing | Hot rolling mill and TMT mill equipment manufacturing. PPRM partnered with Realization to achieve a year-on-year rise in throughput of around 70% by streamlining its internal processes. |
| Trident Group — cotton yarn | Textile | 2 yarn plants were delivered in 16 months, against 1 similar plant delivered in 21 months previously. |
| BluePi | IT & Software | BluePi is strategically transitioning from agile to CCPM methodology for IT projects. The aim is to deliver 20%-30% more projects with the same resources and reduce the actual cycle time of projects by 50%. |
| Vardhman Fabrics | Textile | The first project was delivered on time in 15 months with a 30% additional scope and the second project was delivered on time in 18 months. |
| KPTL — Domestic | EPC Business | KPTL exceeded AOP targets by 20-30%. |
The range
Clients have reduced project cycle time by 25–50%. The figure depends on how much of the delay sits in execution rather than in scope, approvals or supply — which is the first thing an assessment establishes.