Yogiji Digi Group · Manufacturing

Yogiji Digi Group — 37.6% Throughput Increase in 6 Months

Challenges

  • Engineering: design changes and support issues wasted 40% bandwidth.
  • Manufacturing: 4,000–8,000 parts made coordination and procurement difficult.
  • Assembly: missing parts caused frequent switches; cycle time hit 14.2 days.

Our work

  • WIP control: cut active projects from 18 to 11 for smoother flow.
  • Full-Kitting: no assembly started without 100% of parts ready.
  • Bottleneck focus: prioritized assembly, cutting idle time.

Results

  • Throughput: projects up 37.6%, assemblies up 26.7%.
  • Faster completion: project time cut 45%, assembly 28%.
  • Predictability: delays dropped 81% (5.5 months to 23 days).

“We are one of the fastest growing flat steel rolling solutions and equipment manufacturers. We have set some good targets for us like on-time delivery of more than 90% and Y-o-Y growth of around 30% for the next 5 years. We are on track to reduce our cycle time by 45% against the targeted 40%.”

Mr. Aseem Gill, VP Projects, Yogiji Digi Group

Is a critical project slipping?

Tell us about the project at risk of missing its committed date.

Set Up a Discussion