Yogiji Digi Group — 37.6% Throughput Increase in 6 Months
Challenges
- Engineering: design changes and support issues wasted 40% bandwidth.
- Manufacturing: 4,000–8,000 parts made coordination and procurement difficult.
- Assembly: missing parts caused frequent switches; cycle time hit 14.2 days.
Our work
- WIP control: cut active projects from 18 to 11 for smoother flow.
- Full-Kitting: no assembly started without 100% of parts ready.
- Bottleneck focus: prioritized assembly, cutting idle time.
Results
- Throughput: projects up 37.6%, assemblies up 26.7%.
- Faster completion: project time cut 45%, assembly 28%.
- Predictability: delays dropped 81% (5.5 months to 23 days).
“We are one of the fastest growing flat steel rolling solutions and equipment manufacturers. We have set some good targets for us like on-time delivery of more than 90% and Y-o-Y growth of around 30% for the next 5 years. We are on track to reduce our cycle time by 45% against the targeted 40%.”
Mr. Aseem Gill, VP Projects, Yogiji Digi Group