Shyam Metalics · Steel
Shyam Metalics – Long-Shut Steel Complex Restarted and Commissioned in 16 Months
Challenges
- Long-closed steel complex with incomplete engineering and missing drawings
- Procurement delays with 40–70 POs delayed by 45+ days
- L1-based supplier selection without capacity validation
- Fragmented material delivery causing start–stop execution
- Partial civil handovers leading to rework and congestion
- Manpower mobilization at only 60–70% of required strength
- Mid-phase scope changes adding ~60 days delay
Our work
- Restructured ordering into system-wise construction batches
- Closed budget gaps and fast-tracked long-lead approvals
- Introduced strict Full-Kit readiness before releasing work fronts
- Reorganized manpower to focus on high-impact zones
- Sequenced material dispatch aligned to erection order
- Shifted tracking from activity-based to velocity-based control
Results
- Mechanical completion achieved within 11 months
- Execution velocity improved to near-required levels
- Procurement throughput improved from ~50% to ~70%
- Vendor delivery adherence exceeded 90% in the final quarter
- Major work zones achieved 90%+ planned execution speed