Shyam Metalics – Long-Shut Steel Complex Restarted and Commissioned in 16 Months

Challenges

  • Long-closed steel complex with incomplete engineering and missing drawings
  • Procurement delays with 40–70 POs delayed by 45+ days
  • L1-based supplier selection without capacity validation
  • Fragmented material delivery causing start–stop execution
  • Partial civil handovers leading to rework and congestion
  • Manpower mobilization at only 60–70% of required strength
  • Mid-phase scope changes adding ~60 days delay

Our work

  • Restructured ordering into system-wise construction batches
  • Closed budget gaps and fast-tracked long-lead approvals
  • Introduced strict Full-Kit readiness before releasing work fronts
  • Reorganized manpower to focus on high-impact zones
  • Sequenced material dispatch aligned to erection order
  • Shifted tracking from activity-based to velocity-based control

Results

  • Mechanical completion achieved within 11 months
  • Execution velocity improved to near-required levels
  • Procurement throughput improved from ~50% to ~70%
  • Vendor delivery adherence exceeded 90% in the final quarter
  • Major work zones achieved 90%+ planned execution speed