Century Panels · Building materials

Century Panels – MDF and Laminate Plants Commissioned in 16.5 Months

Challenges

  • Monsoon delays caused a 2.5-month setback, hindering initial site execution and equipment movement.
  • Severe manpower shortages, with only 30% of civil resources mobilized during critical phases.

Our work

  • Developed a Focus & Finish strategy to ensure clean handovers and avoid premature starts.
  • Prioritized MDF plant completion, reallocating resources from the laminate plant to address civil manpower shortages.

Results

  • Laminate plant commissioned and operational in 14 months.
  • MDF plant commissioned and operational in 16.5 months, despite significant delays.

“We started our implementation with Realization in October 2022 for our ₹1100 Cr. Greenfield expansion project of MDF and Laminate plants in Kadapa, Andhra Pradesh, when site execution had just started. Along with Realization, we set an aggressive target of 14 months for the production of the first board. Right at the start, the retreating monsoons and its impact on the site, held up work for nearly 3 months.

Due to the location of the project, mobilizing civil manpower was a major challenge. Following the impact of weather, we could only mobilize 30% of the required resources. Apart from these major factors, we faced the usual weather, festival issues, late discovery of scope, delays in drawings and supplies etc. that typically amplifies the delays. Yet, we recovered, and the first board was produced in 16.5 months, only 2.5 months beyond the original target.”

Mr. Keshav Bhajanka, Executive Director, Century Panels