BRPL · Power
BRPL – HGMS Project Delivered On-Time Against a 30% Faster Target
Challenges
- Plant shutdown needed for HGMS upgradation.
- Timeline pressure to recover Fe and enable RM.
- Delays in engineering, ordering, and equipment delivery.
- Civil manpower shortage affected execution.
Our work
- Focus & Finish plan in two weeks.
- Mapped processes, identified risks, prioritized engineering.
- Enabled decision making on workstreams and created what-if scenarios for shutdown planning.
- Staggered commissioning of HGMS for minimal disruption.
Results
- Timeline and risks established within two weeks.
- Lead time reduced by loaning HGMS units.
- Staggered HGMS commissioning minimized disruptions.
- Project completed within the original 14-month timeline.
“Realization Technologies proved instrumental in upgrading our Barbil beneficiation plant with the addition of an HGMS (high-gradient magnetic separation) system. Within just two weeks of engagement, they created a comprehensive project plan, aligned timelines & processes with all stakeholders. Their proactive identification of risk areas and mitigation strategies set a solid foundation for success. Today, we are well on our way to complete the project within the original timeline of 14 months. With their unique multi-tiered planning approach, we maintained control of execution and remained confident in achieving our targets. The Focus-and-Finish methodology provided clear guidance for teams, empowering us to execute projects with minimal manual coordination. Streamliner is easy to understand & adapt to in project environments.”
PR Prasad, Director Steel, Lloyd Steels; former MD, BRPL
Is a critical project slipping?
Tell us about the project at risk of missing its committed date.
Set Up a Discussion