BRPL · Power

BRPL – HGMS Project Delivered On-Time Against a 30% Faster Target

Challenges

  • Plant shutdown needed for HGMS upgradation.
  • Timeline pressure to recover Fe and enable RM.
  • Delays in engineering, ordering, and equipment delivery.
  • Civil manpower shortage affected execution.

Our work

  • Focus & Finish plan in two weeks.
  • Mapped processes, identified risks, prioritized engineering.
  • Enabled decision making on workstreams and created what-if scenarios for shutdown planning.
  • Staggered commissioning of HGMS for minimal disruption.

Results

  • Timeline and risks established within two weeks.
  • Lead time reduced by loaning HGMS units.
  • Staggered HGMS commissioning minimized disruptions.
  • Project completed within the original 14-month timeline.

“Realization Technologies proved instrumental in upgrading our Barbil beneficiation plant with the addition of an HGMS (high-gradient magnetic separation) system. Within just two weeks of engagement, they created a comprehensive project plan, aligned timelines & processes with all stakeholders. Their proactive identification of risk areas and mitigation strategies set a solid foundation for success. Today, we are well on our way to complete the project within the original timeline of 14 months. With their unique multi-tiered planning approach, we maintained control of execution and remained confident in achieving our targets. The Focus-and-Finish methodology provided clear guidance for teams, empowering us to execute projects with minimal manual coordination. Streamliner is easy to understand & adapt to in project environments.”

PR Prasad, Director Steel, Lloyd Steels; former MD, BRPL