BUIDCo · Infrastructure
BUIDCo – 681 km Work Front Released in 6 Months Across 15 Cities
Challenges
- Severe work area limitation: only 180 km available for a 2200 km project scope.
- Frequent disruptions: poor planning caused extended timelines and constant delays.
- Escalating costs: frequent redesigns and emergency procurement led to significant cost overruns.
- Serious safety concerns: rushed construction heightened the risk of accidents and injuries.
Our work
- Secured land, approvals, and resources in the Pre-Full Kit phase, setting strong project foundations.
- Executed comprehensive planning and stakeholder engagement during Project Full Kit.
- Streamlined Section Full Kit with strategic approvals and resource allocation.
- Optimized execution with 15-day forecasts, delay buffers, and a centralized Project Execution Office.
Results
- Optimized resource allocation, cut costs by reducing rework, and enhanced safety.
- Land cleared: 68 in Nov 2012 against 22 in April 2012.
- Designs approved: 33 in Nov 2012 compared to nil in April 2012.
- Release of 681 km of work front in 6 months and doubled the design approval rate.