BUIDCo – 681 km Work Front Released in 6 Months Across 15 Cities

Challenges

  • Severe work area limitation: only 180 km available for a 2200 km project scope.
  • Frequent disruptions: poor planning caused extended timelines and constant delays.
  • Escalating costs: frequent redesigns and emergency procurement led to significant cost overruns.
  • Serious safety concerns: rushed construction heightened the risk of accidents and injuries.

Our work

  • Secured land, approvals, and resources in the Pre-Full Kit phase, setting strong project foundations.
  • Executed comprehensive planning and stakeholder engagement during Project Full Kit.
  • Streamlined Section Full Kit with strategic approvals and resource allocation.
  • Optimized execution with 15-day forecasts, delay buffers, and a centralized Project Execution Office.

Results

  • Optimized resource allocation, cut costs by reducing rework, and enhanced safety.
  • Land cleared: 68 in Nov 2012 against 22 in April 2012.
  • Designs approved: 33 in Nov 2012 compared to nil in April 2012.
  • Release of 681 km of work front in 6 months and doubled the design approval rate.