Prism Cement · Cement
Prism Cement – Combined Upgrade and Annual Shutdown Delivered 13 Days Early
Challenges
- A major upgrade of the Unit 2 preheater at Satna coincided with the plant’s annual maintenance shutdown, and management combined the modification tie-ins and the maintenance work into one stoppage.
- Fewer plant stoppages, but concentrated execution risk: duct erection, cyclone rotation, refractory work, structural changes, feed systems, fans, electrical work and annual maintenance shared the same access, lifting routes, contractor capacity and final commissioning date.
- The shutdown had to be completed before the available clinker stock was exhausted; beyond that point the interruption could affect cement production outside Unit 2.
- Estimated exposure of approximately INR 1–1.5 crore for each additional day after clinker depletion.
- More than 200 activities across over 20 stakeholder and contractor interfaces, dependent on shared workfronts, access, lifting routes and contractor capacity.
- Floor cutting, scaffolding, cyclone work, duct erection and refractory removal all requiring the same 44 m elevation and access routes.
Our work
- Ran an initial analysis and planning workshop with the project head, operations, maintenance, E&I, departmental heads and principal vendors.
- Built the shutdown sequence backward from trial and commissioning on a shared board, defining each physical handover and challenging its duration, workfront, resource requirement and readiness condition.
- Moved approximately 30% of floor cutting at 44 m ahead of shutdown, reducing the in-shutdown requirement from about 18 days to 7–8 days.
- Targeted the main duct between 50 m and 66 m for early mechanical handover so refractory work could begin before shutdown.
- Deployed a separate vendor for non-preheater workstreams and completed day-wise manpower planning with each vendor.
- Reorganised more than 200 detailed activities into 35 handover batches, each ending in a physical output required by the next team, within a 63-day Focus and Finish Plan including a seven-day project buffer.
- Defined a full-kit for each batch covering engineering, access, lifting, equipment, manpower and workfront conditions, and deferred the shutdown until pre-shutdown activities and full-kits were reported as 100% ready.
- Broke vendor commitments into day-wise, shift-wise and selected 6-to-12-hour blocks, planning Cyclone 5 rotation as an 11-activity, 11-day sequence with manpower and lifting readiness defined by shift.
- Measured execution through the cycle time of each handover batch, separating a delay in releasing a batch from a delay in executing the work, with daily reviews triggering recovery at the relevant workfront.
Results
- The integrated preheater upgrade and annual shutdown ran from 11 January to 1 March 2026.
- Completed in 50 days against the approved 63-day execution plan — 13 days earlier, a 20.6% reduction against plan.
- Completion was achieved despite overruns in several individual critical activities.