Tata Steel · Steel

Tata Steel – Finishing Mill Upgrade Completed Ahead of Schedule, $4.4M Saved

Challenges

  • Stubborn foundation bolts threatening the timeline
  • Critical motor alignment under severe time pressure
  • Single crane bottleneck risking project flow
  • 500+ interdependent tasks demanding precise coordination
  • Unforeseen disruptions from an unrelated project

Our work

  • Single crane optimization through strict allocation rules
  • Focus & Finish batches managing 500+ interdependent tasks
  • Swift recalibration addressing unexpected pipeline project impact

Results

  • Completed in 8.8 days, against the target of 11 days
  • Saved $4.4 million in potential revenue loss

“We needed to complete the project in 11 days against baseline performance of 15 days. Operations team had to be onboarded during the same time. We were able to complete Hot Strip Mill shutdown in 8.8 days against plan of 11 days.”

Mr. Sudipto Sarkar, Head TQM, Tata Steel