Tata Steel · Steel
Tata Steel – Finishing Mill Upgrade Completed Ahead of Schedule, $4.4M Saved
Challenges
- Stubborn foundation bolts threatening the timeline
- Critical motor alignment under severe time pressure
- Single crane bottleneck risking project flow
- 500+ interdependent tasks demanding precise coordination
- Unforeseen disruptions from an unrelated project
Our work
- Single crane optimization through strict allocation rules
- Focus & Finish batches managing 500+ interdependent tasks
- Swift recalibration addressing unexpected pipeline project impact
Results
- Completed in 8.8 days, against the target of 11 days
- Saved $4.4 million in potential revenue loss
“We needed to complete the project in 11 days against baseline performance of 15 days. Operations team had to be onboarded during the same time. We were able to complete Hot Strip Mill shutdown in 8.8 days against plan of 11 days.”
Mr. Sudipto Sarkar, Head TQM, Tata Steel
Is a critical project slipping?
Tell us about the project at risk of missing its committed date.
Set Up a Discussion