Boeing · Aerospace

Boeing Satellite Unit – Throughput Doubled, Cycle Time Cut by 30%

Challenges

  • Uniquely complex product set
  • Two to three spacecraft per program
  • High cost
  • Product cannot be serviced

Our work

  • Prioritize resource allocation
  • Set priorities based on the critical chain
  • Proactive decision-making from system alerts
  • Manage WIP

Results

  • Overall large reductions in cost (20-30%) and cycle times
  • One project finished in 65 days against the expected 92
  • A unit-level design project finished in 70% of the time allocated