Vulcan · Mining
Vulcan Mozambique – Achieved 40% Higher Maintenance Hours
Challenges
- Obvious strategies would not work
- No control over strategy
- De-synchronization issues
- Resource unpredictability
Our work
- Focus & Finish packages
- Streamlined execution through contractor onboarding
- Streamliner as the enabler
Results
- Actual shutdown hours were completed for 80 of 81 packages
- Reduced firefighting
“Vulcan aimed to triple met coal production at Moatize in 14 months. With 17 brownfield projects identified, including 2 thickener projects, Realization's Focus-&-Finish method streamlined execution. By prioritizing one project at a time, Vulcan achieved efficient results, with the first project completed in 260 days (vs. 340 days projected) and the second, with expanded scope, in just 135 days. Shutdown tie-ins were also completed punctually.”
Mr. Rajender Tiwari, Executive Vice President, Vulcan International