Transmission & Distribution · Power

Transmission & Distribution — A Common Execution Desync Seen Across Live Projects

Challenges

  • Severe desynchronization across functions such as design, ROW, foundation, erection, and supply, each working independently.
  • Conflicting KPIs where teams optimized for local targets (for example, towers fabricated or foundations completed) instead of overall project flow.
  • Reactive site decisions where field teams shifted locations based on ease of access, breaking planned continuity.
  • Fragmented monitoring with progress tracked through multiple spreadsheets, preventing early detection of misalignment.
  • Weak coordination as meetings focused on review rather than problem-solving, and no shared view of sequence or priorities existed.

Our work

  • Introduced the Focus & Finish execution system to drive synchronization across all functions.
  • Developed integrated batch-level plans linking design release, material dispatch, ROW clearance, and foundation readiness.
  • Replaced numeric KPIs with outcome-based metrics such as the number of stringing-ready sections and velocity (planned versus actual duration).
  • Conducted weekly cross-functional reviews focused on conflict resolution and sequence alignment.
  • Enabled data-driven visibility to prioritize work fronts for continuous stringing and faster energization.

Results

  • KPTL implemented the approach across Africa, Ukraine, Bhutan, and India and achieved a 30–40% improvement over AOP targets.
  • GR Infra adopted the model for all power transmission and distribution projects from September 2025 onward.
  • Improved velocity and predictability of project completion through synchronized execution flow.