Transmission & Distribution · Power
Transmission & Distribution — A Common Execution Desync Seen Across Live Projects
Challenges
- Severe desynchronization across functions such as design, ROW, foundation, erection, and supply, each working independently.
- Conflicting KPIs where teams optimized for local targets (for example, towers fabricated or foundations completed) instead of overall project flow.
- Reactive site decisions where field teams shifted locations based on ease of access, breaking planned continuity.
- Fragmented monitoring with progress tracked through multiple spreadsheets, preventing early detection of misalignment.
- Weak coordination as meetings focused on review rather than problem-solving, and no shared view of sequence or priorities existed.
Our work
- Introduced the Focus & Finish execution system to drive synchronization across all functions.
- Developed integrated batch-level plans linking design release, material dispatch, ROW clearance, and foundation readiness.
- Replaced numeric KPIs with outcome-based metrics such as the number of stringing-ready sections and velocity (planned versus actual duration).
- Conducted weekly cross-functional reviews focused on conflict resolution and sequence alignment.
- Enabled data-driven visibility to prioritize work fronts for continuous stringing and faster energization.
Results
- KPTL implemented the approach across Africa, Ukraine, Bhutan, and India and achieved a 30–40% improvement over AOP targets.
- GR Infra adopted the model for all power transmission and distribution projects from September 2025 onward.
- Improved velocity and predictability of project completion through synchronized execution flow.