Jindal Paradip Port – Phase 1 Delivered Ahead of Schedule

Challenges

  • Work was progressing across all coal fronts, but no single route from jetty to yard to silo to rail was close to operable.
  • Three cranes shared across all coal transfer towers and conveyors, causing remobilisation losses and waiting between dependent structures.
  • Both 60-metre silos under construction simultaneously, splitting manpower, shuttering/staging material and crane capacity.
  • Design of LTT-2, the transfer tower connecting jetty and yard conveyors, was pending. Conveyor structure fabrication incomplete and material not supplied.
  • Phase-1 projected to April 2026 against an October 2025 business start-up requirement, with the monsoon window approaching.

Our work

  • Mapped all coal circuits end-to-end, from jetty to railway, to identify the route closest to closure.
  • Designated the shortest-duration route (CT1–CTT1–CTT2–CTT7–CTT6–CTT5–CTT8 silo and rail interface) as the Phase-1 operational circuit.
  • Closed LTT-2 civil and structural design on priority.
  • Realigned fabrication sequencing and material dispatch to the circuit’s readiness order instead of general bulk supply.
  • Mobilised additional cranes and assigned them to specific towers on the Phase-1 circuit.
  • Stopped civil work on the second silo and concentrated all civil manpower, shuttering/staging material and crane on completing the first.
  • Prioritised and batched coal-serving interfaces at the jetty while other areas continued in parallel.

Results

  • First physically continuous coal stacking circuit structurally completed by August 2025.
  • Entire jetty completed by July 2025, aligned with coal system readiness.
  • Structural erection output rose from the 328-394 tonne range in October-December to 1,230 tonnes in March.