Jindal · Ports
Jindal Paradip Port – Phase 1 Delivered Ahead of Schedule
Challenges
- Work was progressing across all coal fronts, but no single route from jetty to yard to silo to rail was close to operable.
- Three cranes shared across all coal transfer towers and conveyors, causing remobilisation losses and waiting between dependent structures.
- Both 60-metre silos under construction simultaneously, splitting manpower, shuttering/staging material and crane capacity.
- Design of LTT-2, the transfer tower connecting jetty and yard conveyors, was pending. Conveyor structure fabrication incomplete and material not supplied.
- Phase-1 projected to April 2026 against an October 2025 business start-up requirement, with the monsoon window approaching.
Our work
- Mapped all coal circuits end-to-end, from jetty to railway, to identify the route closest to closure.
- Designated the shortest-duration route (CT1–CTT1–CTT2–CTT7–CTT6–CTT5–CTT8 silo and rail interface) as the Phase-1 operational circuit.
- Closed LTT-2 civil and structural design on priority.
- Realigned fabrication sequencing and material dispatch to the circuit’s readiness order instead of general bulk supply.
- Mobilised additional cranes and assigned them to specific towers on the Phase-1 circuit.
- Stopped civil work on the second silo and concentrated all civil manpower, shuttering/staging material and crane on completing the first.
- Prioritised and batched coal-serving interfaces at the jetty while other areas continued in parallel.
Results
- First physically continuous coal stacking circuit structurally completed by August 2025.
- Entire jetty completed by July 2025, aligned with coal system readiness.
- Structural erection output rose from the 328-394 tonne range in October-December to 1,230 tonnes in March.