Siemens Gamesa · Wind energy

Siemens Gamesa: ~50% Reduction in Design Cycle Time in High-Uncertainty R&D

Context

Siemens Gamesa operates in a high-uncertainty R&D environment, developing wind turbine platforms involving multiple engineering disciplines: mechanical, electrical, hydraulics, aero design, manufacturing, procurement, and quality. Typical R&D cycle times were approximately two years, with increasing pressure to reduce this to nearly one year, implying a ~50% reduction driven by market demands.

Business challenge

Despite strong engineering capability, planning and execution were consistently constrained by structural issues. There was high uncertainty in scope and sequence of work, and iterative design cycles often led to spillovers across phases, commonly referred to as “travelled work.” At the same time, there was limited visibility into how work actually flowed across functions.

Planning was heavily dependent on static, complex schedules that were difficult to build and maintain, and in practice were rarely followed during execution. Given this complexity, teams defaulted to local optimization, focusing on what was manageable at an individual level rather than what was optimal for the system.

In practical terms, this translated into significant execution inefficiencies. Projects planned for a few months could extend dramatically, with one instance stretching from 2.5 months to 2.5 years. Milestone tracking at actionable levels was weak, and re-prioritization became frequent and reactive.

Intervention: change started from planning itself

Instead of forcing detailed planning upfront, Siemens Gamesa shifted its approach by implementing a Two-Tier Task structure.

At the first level, the entire R&D cycle was structured into approximately 50 Tier-1 tasks. Each of these tasks clearly defined inputs, outputs, and the required cross-functional team. Importantly, this level avoided forcing micro-level sequencing and was designed to be intuitively understood and validated by experts. This simplicity enabled senior experts to review and validate the entire process within minutes, creating alignment and clarity across the organization.

At the second level, detailed execution was managed within each Tier-1 block. These Tier-2 tasks were typically maintained within a duration of one to three weeks, allowing teams to retain flexibility in handling changing sequences, design iterations, and inherent engineering uncertainty.

How the approach addressed core challenges

Uncertainty in scope and work sequencing was absorbed at the Tier-1 level, where the focus remained on defining what needed to be achieved rather than prescribing an exact sequence. Design iterations and spillovers were reduced by grouping related work into logical blocks executed by the same teams, minimizing cross-phase rework. Cross-functional alignment improved as each Tier-1 task inherently defined the required disciplines and inputs.

At the same time, planning effort was significantly reduced. Instead of building large, static schedules with thousands of line items, planning shifted toward establishing structural clarity.

Execution approach

The planning process began by mapping the actual workflow through structured sessions with domain experts. This was done iteratively using workshops, post-it mapping, and repeated validation loops until a consistent structure emerged.

Duration estimates were based on expert judgment and were found to be within approximately ±10% accuracy. To manage uncertainty, task durations were reduced to around 70% of the estimated time, with the remaining uncertainty absorbed through an aggregated buffer of approximately 30%.

Key learning

Clarity at the right level matters more than excessive detail. Tier-1 structure provided the alignment and confidence required for execution, while Tier-2 handled variability where it actually existed. Organizations often do not have an explicit understanding of how work flows, as critical knowledge typically resides within experts. Structuring this knowledge creates immediate value.

Challenges

  • High uncertainty in scope and sequencing of R&D work
  • Frequent design iterations causing rework
  • Limited visibility into end-to-end workflow across functions
  • Over-reliance on complex, static plans not followed in execution
  • Local optimization instead of system-level focus
  • Weak milestone tracking and execution control
  • Reactive re-prioritization leading to timeline overruns

Our work

  • Implemented a Two-Tier Task planning framework
  • Defined ~50 Tier-1 tasks with clear inputs, outputs, and ownership
  • Enabled flexible execution via short-cycle Tier-2 tasks (1–3 weeks)
  • Mapped actual workflows through expert-led workshops
  • Reduced over-detailed planning; focused on structural clarity
  • Introduced buffer-based planning to manage uncertainty
  • Aligned teams to optimize flow, not individual tasks

Results

  • ~50% reduction in design cycle time
  • Significant reduction in rework and spillovers
  • Improved cost and quality adherence
  • Stronger cross-functional alignment and ownership

“We were under pressure to significantly reduce our R&D cycle times, but the way we were planning and executing projects wasn't supporting that. The plans were complex, difficult to maintain, and in practice, not followed.

What changed for us was shifting away from trying to detail everything upfront. Instead, we structured our work at a higher level, aligned cross-functional teams clearly, and managed execution within that structure.

In our conceptual design phase, we were able to reduce cycle time by roughly 50%, while also improving the quality of our outputs and meeting our cost targets. The approach brought clarity. Our teams could see how the work flows, focus on priorities, and make better decisions without getting lost in the complexity.”

Mr. Robert Fuller, Director of Engineering, Siemens Gamesa