Procter & Gamble · Pharmaceutical

Procter & Gamble Pharmaceuticals – 300% Throughput Increase Per Quarter in a Year

Challenges

  • High uncertainty in drug development, causing frequent delays and plan changes
  • Projects often delivered late due to unpredictable risks and changing timelines
  • Limited resources despite increasing number of projects
  • Shared resources across multiple projects leading to multitasking and inefficiency
  • Difficulty in prioritizing projects across the portfolio
  • Poor synchronization due to resource unavailability at the right time
  • Inconsistent throughput and due date compliance
  • Lack of proactive response to early warning signs (buffer consumption)

Our work

  • Provided CCPM software for project execution management
  • Enabled portfolio-level project prioritization and resource allocation
  • Implemented buffer management to track delays and risks early
  • Provided real-time dashboards for monitoring project progress
  • Helped assign clear task priorities to reduce multi-tasking
  • Identified bottlenecks and provided early warning signals
  • Improved resource utilization across multiple projects
  • Supported faster project completion and better due date compliance

Results

  • Due-date compliance improved from 55% to 80%+
  • Project completions increased from 3 projects (Q1 2005) to 8 projects (Q1 2006)
  • Current throughput is 12+ projects per quarter
  • Projects in the system increased from 25 to 41