Procter & Gamble · Pharmaceutical
Procter & Gamble Pharmaceuticals – 300% Throughput Increase Per Quarter in a Year
Challenges
- High uncertainty in drug development, causing frequent delays and plan changes
- Projects often delivered late due to unpredictable risks and changing timelines
- Limited resources despite increasing number of projects
- Shared resources across multiple projects leading to multitasking and inefficiency
- Difficulty in prioritizing projects across the portfolio
- Poor synchronization due to resource unavailability at the right time
- Inconsistent throughput and due date compliance
- Lack of proactive response to early warning signs (buffer consumption)
Our work
- Provided CCPM software for project execution management
- Enabled portfolio-level project prioritization and resource allocation
- Implemented buffer management to track delays and risks early
- Provided real-time dashboards for monitoring project progress
- Helped assign clear task priorities to reduce multi-tasking
- Identified bottlenecks and provided early warning signals
- Improved resource utilization across multiple projects
- Supported faster project completion and better due date compliance
Results
- Due-date compliance improved from 55% to 80%+
- Project completions increased from 3 projects (Q1 2005) to 8 projects (Q1 2006)
- Current throughput is 12+ projects per quarter
- Projects in the system increased from 25 to 41