Jindal Sohar – 72-Meter Iron Ore Grinding Ball Mill Commissioned in 6 Months

Challenges

  • Project completion date was slipping repeatedly with no stable commissioning target.
  • Multiple major scopes were running in parallel in a highly constrained working area.
  • Common crane movement zones created frequent clashes and daily coordination issues.
  • Structural manpower was lower than required for the remaining scope.
  • Commissioning teams were spread across several partially completed systems.

Our work

  • Reviewed remaining scope, site constraints, manpower, and system dependencies.
  • Defined a clear priority milestone: commissioning of Dry Mill-1.
  • Stopped Dry Mill-2 erection and redirected resources to off-site readiness.
  • Dedicated site access and cranes exclusively to Dry Mill-1.
  • Reorganized commissioning to close systems one by one.
  • Enforced full-kitting before releasing work fronts.

Results

  • Completed Dry Mill-1 erection and first-stage commissioning in six months.
  • Delivered two months faster than typical industry timelines.

“Realization India supported us in project controls during the execution of the Jindal Steel Sohar Pellet Project and played an important role in helping us complete the project as per the committed timelines.

The Realization team worked closely with our site and project teams to identify key constraints and remove them through decisive and collaborative planning. The introduction of full-kitting discipline significantly improved overall work flow at site. Their contribution had a clear and meaningful positive impact on the project.”

Mr. Vimal Malhotra, Vice President, Jindal Pelletizing LLC