VIBGYOR Group of Schools · Education

Vibgyor Schools: 70% Reduction in Cycle Time with 90%+ On-Time Delivery

Challenges

  • Brownfield cycle time had stretched to 8 months.
  • 35 brownfield and 2 greenfield projects under simultaneous load.
  • Design teams overloaded with parallel school-wise work.
  • Annual requirement inflow arrived in waves, creating backlog.
  • Revamp projects pending since 2019 due to lack of execution window.
  • Cashflow constraints and unstructured vendor payments.
  • Execution started without complete drawings or POs.
  • Greenfield progress exposed to statutory approval uncertainties.

Our work

  • Limited active work-in-progress to 6 projects at a time.
  • Introduced clear priority sequencing (Admissions → Compliance → Others).
  • Implemented structured annual demand consolidation workshop.
  • Rationalized and internalized repetitive design work.
  • Closed projects school-by-school instead of parallel partial progress.
  • Enforced execution readiness before project start.
  • Linked cashflow reviews and payment release to defined priority list.

Results

  • Brownfield cycle time reduced from 8 months to 2.5 months (70% reduction).
  • Greenfield projects initiated in January 2025 as planned.
  • Revamp projects pending since 2019 scheduled for execution.
  • Annual requirement inflow reduced from 380 to 190.
  • Achieved 90%+ on-time delivery across the portfolio.
  • Restored predictable capacity planning and portfolio control.

“Managing multiple brownfield as well as greenfield projects was creating a lot of problems for us. Projects that were expected to be completed within three months were dragging on for six months. The projects used to stretch endlessly.

The change came with Realization's Focus & Finish approach. Instead of running everything at the same time, projects were staggered in a planned manner. We finished certain projects before starting others.

As a result, we were able to complete our projects on time, without our teams getting distracted or our energies being spread thin. Most importantly, we were able to start our schools on time.”

Mr. Rustom Kerawalla, Chairman, Vibgyor Schools