CCPM implementation · Pharmaceutical R&D
The hidden constraint in pharma R&D
It is not the science. It is how much work is released into execution at once.
Improving R&D Portfolio Flow and Due Date Performance at Granules India
The situation
A pharmaceutical R&D portfolio runs many projects at once, over shared specialist resources, with scientific uncertainty built into the work. When a project is released into execution as soon as it is prioritised — before the materials, the decisions and the scientist capacity are in place — work in progress rises, execution runs stop-start, and completion dates become difficult to hold.
What a CCPM implementation changes
In June 2025, Granules India began a Critical Chain Project Management implementation with Realization across its API and Formulation Development R&D portfolios. The portfolio team continued to set business priority. Three things changed in how that priority became work.
What is now standard practice
Direct allocation of development scientists to active projects, controlled project release, Full-Kit preparation, integrated project planning and structured execution reviews are now part of how the portfolio is run. The cycle-time-linked measurement system has been agreed. Granules India also achieved its FY 2025-26 portfolio targets.
Does this describe your R&D portfolio?
- You cannot tell the business which projects will hit their committed date.
- Scientists are spread across several projects, so every project waits for one.
- Work is released the moment it is prioritised, not when it is ready to run.
- Dependencies and risks surface in the review, not before it.
What changed
Release matched to capacity
Projects were separated into active execution, preparation and hold queues. The number running at once was aligned to the capacity of development scientists — the resource constraining portfolio flow — and scientists were allocated directly to active projects so work would not wait for availability.
Full Kit before release
No project entered execution until its readiness conditions were met: scope and target, approved development plan, materials and reference standards, analytical and documentation readiness, facility or equipment availability, acceptance criteria, critical decisions and confirmed functional resources. Inputs needed by the next resource group were identified in advance.
One plan, and reviews on cycle time
API and FD project networks were integrated in Streamliner to reflect dependencies, signal execution and show expected completion dates and risks. Reviews moved onto cycle-time performance, emerging constraints and corrective actions, reinforced by a cycle-time-linked measurement system.
Granules India · fifteen months
Projects delivered on the committed date
- Scientist turnaround time18 months→14 months
- Project cycle time22 months→20 months
- Projects in active execution — Formulation Development11→7
- Projects in active execution — API10→8
“Now we commit a date with confidence once all these are kept ready.”
Dr. R. Manikandan, Senior Vice President and Head, R&D (Formulation Development), Granules India
- 90%due-date performance
- 11–12months scientist turnaround
- 10project deliveries a year
Is a critical project slipping?
Tell us about the project at risk of missing its committed date.
Set Up a Discussion