Execution Management Minute
Learn practical execution management strategies to reduce project delays, improve coordination, and accelerate project delivery with Realization India.
Putting the Pipelining Rule into practice
In this minute we outline how to apply the Pipelining Rule to multi-project environments. The Pipelining Rule is to concentrate resources on a few projects or work streams. Its benefits are fewer shortages of resources, more attention from experts and managers to resolve problems, and faster completion. It also allows you to do more projects with the same resources, as work flows faster with fewer interruptions. This rule is typically put into practice in two steps.
Step 1: transition to low WIP
- Temporarily freeze 25% of the projects (by workload), both in the overall pipeline and in the system integration and testing (SI&T) phase.
- Accelerate remaining projects using a simple priority process, for example project due dates.
- Deploy any remaining resources on full-kitting (preparing for execution) the frozen projects.
- As in-process projects are completed, unfreeze the frozen projects one by one.
- Avoid paralysis by analysis. The goal is to start getting results within 3 weeks.
Step 2: establish a pipelining process
- Set targets for cycle time by project type. This ensures that projects are planned with concentrated resources.
- Decide on the pacing resource. The pacing resource determines the rate at which projects can be completed, and started, in execution. Typically overall throughput is determined by the rate of project completion in the SI&T phase, because of the considerable effort spent synchronizing resources and resolving problems as they are found. In very few cases an upstream resource or phase is the constraint and should be the pacing resource instead.
- Establish a management meeting for setting project priorities and committing due dates. Typically a dedicated master scheduler or pipeline analyst is required for analytical support.
- Close the loop with a resource planning process that ensures enough of all the other resources are available. This may require creating additional resource flexibility in the organization to support execution of the pipeline plan.
Implementing the Buffering Rule (project planning)
While it is obvious that project plans are needed to provide execution priorities and early warning signals, many organizations struggle with creating useful and manageable project plans.
What comprises an execution-ready project plan?
- Tasks, task duration and resource type or resource units needed for the task
- Checklist below the tasks (optional)
- Dependencies between tasks
- Task managers
- Buffers: feeding buffers, contractual milestone buffers and project buffers
- Resource types and the maximum units of a resource type available to the project
- Project-end and contractual milestone dates
How much detail is required?
Too many tasks in a project plan induce multitasking, make analysis of plans and buffer consumption difficult, and generally lead to loss of control. Not enough detail, on the other hand, encourages unnecessary safeties and Parkinson’s Law, and also leads to loss of control.
Based on our experience across a wide range of projects, more than 300 tasks in a complex project is not recommended — a task taking less than 2% of the project’s lead time needs a very good reason to be in the plan. Nor is fewer than 10 tasks for a simple project, where a task taking more than 5% of lead time also needs a good reason. If this rule of thumb yields tasks that are too long to be useful for task managers, use subprojects to zoom into detail rather than adding tasks to the main project.
What is the process of creating good plans?
- In a multi-project situation, derive cycle time targets based on throughput goals.
- Communicate to all managers that people will not be measured in execution against the task estimates used in planning.
- Assemble a team of the project manager and representative task managers, and run a workshop to get their buy-in to the three rules.
- Create basic project plans, without buffers. In repetitive environments these can be stored as templates.
- Convert basic plans into buffered plans: stagger tasks based on resource availability and insert buffers in the required places.
- Challenge and refine assumptions whenever the calculated project cycle time does not match the expected result.
- Share the final plan with all task managers so they understand their tasks as well as the overall plan.
Points to remember
- A project plan is not a time reporting or effort tracking mechanism. Its purpose is to provide execution priorities and early warning signals.
- A project plan is not a technical manual or a reminder list. A task represents a chunk of work. It should not be broken into several tasks just because it requires different resources for different durations. However, it should be broken down for chosen key resource types.
- Don’t model noise such as lead and lag relationships between tasks for fractional resources. In the uncertain world of projects, reality will often override such sophistication.
Implementing buffer management (prioritizing and managing tasks)
Absence of task-level priorities is a major shortcoming in traditional project management. Now that we can issue clear, uniform and stable task priorities using Rule 3 — tasks consuming the most buffer get the highest priority — what is the management process around them?
1. Remaining duration report
During execution, task managers provide daily estimates of how much longer it will take to finish their tasks in progress. With this simple information, we can calculate the ratio of buffer consumed for a chain of tasks compared to the work completed in that chain. This ratio is then used to calculate task priorities and give task managers a report of all current and upcoming tasks in order of priority. Tendencies to procrastinate and not report early finishes are also curbed: when buffer consumption is high and visible to everyone, it reminds task managers to make and report progress.
2. Resource assignment
Task managers assign resources to current tasks in order of priority. If resources are not enough to handle even the red tasks — those that have crossed the threshold of acceptable buffer consumption — overtime and similar decisions are implemented.
3. Task preparation
After taking care of current tasks, task managers turn their attention to upcoming ones. They make sure all necessary preparations, such as approvals, drawings and materials, are made so tasks can be executed without interruption when they arrive.
4. Quick issue resolution
By interacting with resources for remaining duration updates, task managers discover unexpected problems quickly. They now have a chance to resolve them in a timely manner on an ongoing basis, instead of fighting fires towards the end.
5. Reminder: don’t pressurize resources to meet planning estimates
Otherwise you will soon be back to square one.
Implementing and reinforcing good task management is the key to sustained improvements in project performance.
Is a critical project slipping?
Tell us about the project at risk of missing its committed date.
Set Up a Discussion