Reducing Project Cycle Time in High-Stakes Environments: A U.S. Air Force Case

See how CCPM software helped the U.S. Air Force reduce C-5 maintenance turnaround time from 240 to 160 days and improve project execution.

Silicon India

The Lockheed C-5 fleet formed a critical part of the Iraq and Afghanistan war effort for the U.S. Air Force in the early 2000s. The planes formed an integral part of the war as they carried heavy cargo in the warzone. During crunch time, the heavy intercontinental-range C-5s of the USAF were spending a significant time in the maintenance depots rather than in the field. Short on time, the Air Force called up Realization Technologies, a project planning and execution software provider headquartered in San Jose, California. Leveraging Realization’s CCPM software, the turnaround time for plane maintenance was shortened from 240 days to 160 days, with instances of defects decreased by 75 percent. As a result, the Air Force could deploy additional C-5s in the field, providing the critical logistical support that the US needed.

This is just one example of how Realization Technologies, founded by Sanjeev Gupta fifteen years ago, has been reducing the execution time of projects ranging from high tech and product development to infrastructure and maintenance by 20 to 50 percent.

Source: Silicon India

Read the full article

Is a critical project slipping?

Tell us about the project at risk of missing its committed date.

Set Up a Discussion